Case Study: Fort Bragg Motorpool
MBI 2010 Award Winner![]() |
Building Project Information Ft. Bragg, NCNumber of Modules: 3 Average Size of Modules:
|
Architectural Excellence
The 3572 square foot triple wide modular Motor Pool Dispatching
Office was built and installed in the historical district of Ft. Bragg
and was mandated to meet specific fort historical requirements. The
exterior façade of wainscot and stucco was selected in order to visually
blend with the already existing architecture of the veteran fort.
Approval from the historical society for the cosmetic exterior appearance
and landscape plan was received. Consistent canopies, shingles, stucco
color and some interior selections were required to blend in with local
older buildings. Serving both as administrative offices and central
headquarters for motor pool dispatching operation, the building consists
of seven carpeted offices, two sets of handicapped men and women’s
restrooms, a conference room, a break room, a storage room, easy access
corridors, a dispatch center and a waiting room.
Technical Innovation
The modules for the building were delivered on three separate transports with a hinged roof section pre-built in the factory on modules one and three. Completing this detail in the factory environment saved time and money for the client and resulted in an easy and efficient install. Once the building was crane set the hinged roofs were folded over and the center truss section was installed.
Cost Effectiveness/Energy Efficiency
The pre-hinged roof provided cost efficiency and time savings, not to mention an ingenious solution to simplifying erecting the roof on site. As a temporary building, reuse and relocatability was a factor considered in the building design. Standard size modules for building construction production allowed the customer to occupy the building in less time than standard office construction. Energy efficiency was achieved using R-30 roof insulation, R-19 wall insulation, R-19 floor insulation and low E glass windows. Fire rated sheetrock and fire sprinklers mounted into the drop ceilings were included. Wrapped sheetrock provided durability and efficiency. The short factory production time, quick set-up and finishing once on site lowered the initial set-up costs.



